org, cold joints are a weak spot in the slab and should be avoided if possible.

Things You Will Need

  • Concrete vibrator
  • Reinforcing rod
  • Concrete saw
  • Concrete

Repairing Cold Joints While Pouring Cement

  1. Mix the concrete from the earlier portion of the pour with the fresh concrete, if possible. Use a concrete vibrator to work the two sections into a single mix of concrete as much as possible. How hard, or setup, the first pour of concrete has become will determine if this is possible. If successful, this blending of the two concrete pours will provide the strongest slab that is the least likely to crack.

  2. Place reinforcing rods between the first portion of the slab and the new pour. If the second portion of the pour will be more than two or three hours after the first portion the rebar should be set in the first portion while it is still wet. After the second portion of the concrete is poured, the rebar serves as a connection between the two slabs. The week joint of the cold slab may still crack, but with the rebar connecting the two portions of the slab, the cement will not shift and form a displaced fracture of the cement.

  3. Trowel the cement as smoothly as possible over the cold joint. Cold joints often remain visible after all the concrete has cured due to differences in the color of the concrete.

Repairing Cold Joints in Cured Slabs

  1. Repair small cracks at cold joints with thin mix or a concrete crack sealant. Closing and sealing the cracks prevents water from entering the crack and causing damage through freeze and thaw cycles.

  2. Cut out bigger cracks using a concrete saw. This becomes necessary if the small crack has deteriorated over time and is causing breakage of the concrete, resulting in an open crevice with unstable concrete on the edges. Cut the concrete back far enough so both edges of the opening are high quality cement.

  3. Place reinforcing rods between the two portions of the slab and pour new concrete in place. Trowel to the level of the two slabs and allow to cure.

The Drip Cap

  • By definition a cold joint is a point of connection between two pours of concrete in a slab.
  • Repair small cracks at cold joints with thin mix or a concrete crack sealant.
  • This becomes necessary if the small crack has deteriorated over time and is causing breakage of the concrete, resulting in an open crevice with unstable concrete on the edges.
  • Cut the concrete back far enough so both edges of the opening are high quality cement.
  • Place reinforcing rods between the two portions of the slab and pour new concrete in place.

Photo Credits

man finishing concrete image by jimcox40 from Fotolia.com

man finishing concrete image by jimcox40 from Fotolia.com

Keith Allen

Keith Allen, a 1979 graduate of Valley City State College, has worked at a variety of jobs including computer operator, medical clinic manager, radio talk show host and potato sorter. For over five years he has worked as a newspaper…

Sponsored
HomeSteady Logo

HomeSteady is the ultimate guide for all your household needs, from cleaning and HVAC to electrical, DIY and maintenance.

Property of TechnologyAdvice. © 2026 TechnologyAdvice. All Rights Reserved

Advertiser Disclosure: Some of the products that appear on this site are from companies from which TechnologyAdvice receives compensation. This compensation may impact how and where products appear on this site including, for example, the order in which they appear. TechnologyAdvice does not include all companies or all types of products available in the marketplace.