Suspended solids and other material can form a sludge in the lateral lines and plug the perforations. Septic system maintenance companies clean these lateral lines with high-pressure water inserted into the pipe through a hose. The high-pressure water scours the walls of the pipe and removes the sludge buildup. Broken lateral lines are caused by freezing or being driven over. Lateral lines that are broken, or are not able to be cleaned effectively or economically, will require replacement.

Things You Will Need

  • Shovel
  • 4-inch perforated polyvinyl chloride (PVC) pipe
  • Rake
  • Excavator
  • Skid steer
  • Laser level
  • Septic system design
  • PVC saw
  • Geo-textile fabric
  • PVC primer
  • PVC cement
  1. Remove the topsoil from the rock bed of the drain-field using an excavator.

  2. Pull the existing Geo-textile fabric off the top of the rock bed being careful to keep the topsoil out of the rock layer.

  3. Dispose of the Geo-textile fabric in a municipal debris dumpster.

  4. Locate where the supply pipe attaches to the existing lateral lines in the rock bed and cut the pipe with a PVC saw.

  5. Record the elevation of the lateral pipes with the laser level.

  6. Remove the lateral pipes from the rock bed and dispose of them in a municipal debris dumpster.

  7. Shovel trenches into the rock bed so the elevation of the new pipe will match the original pipe.

  8. Lay the perforated pipe in the rock trenches so that the perforations are pointing downward.

  9. Clean the supply pipe and new lateral pipe with PVC primer.

  10. Coat the supply pipe and new lateral pipe with PVC cement and press together. Twist the pipe ¼ inch and then hold the pipe in place for 30 seconds.

  11. Shovel the drain-field rock around and on top of the newly installed perforated pipe.

  12. Unroll the new Geo-textile fabric onto the rock bed. Install the fabric only on the top, not the sides of the rock bed.

  13. Spread topsoil over excavated are using a tracked skid-steer. Mound the soil over the drain-field to repel surface water.

The Drip Cap

  • After a septic tank anaerobically treats septic waste, the waste water flows through a supply pipe to the lateral lines.
  • The lateral lines then disperse waste water into the rock bed of the drain-field through perforations in the bottom of the pipe.
  • Lay the perforated pipe in the rock trenches so that the perforations are pointing downward.
  • Twist the pipe ¼ inch and then hold the pipe in place for 30 seconds.
  • Mound the soil over the drain-field to repel surface water.

Photo Credits

Jupiterimages/Creatas/Getty Images

Jupiterimages/Creatas/Getty Images

Stephen Hasty

Stephen Hasty started writing in 2009. Covering technical articles and newsletters, his work has appeared in "The Kennebec Valley Plumbing Newsletter" and "Maine Leasing." Hasty holds a bachelor's degree from Saint Cloud State University,…

Sponsored
HomeSteady Logo

HomeSteady is the ultimate guide for all your household needs, from cleaning and HVAC to electrical, DIY and maintenance.

Property of TechnologyAdvice. © 2026 TechnologyAdvice. All Rights Reserved

Advertiser Disclosure: Some of the products that appear on this site are from companies from which TechnologyAdvice receives compensation. This compensation may impact how and where products appear on this site including, for example, the order in which they appear. TechnologyAdvice does not include all companies or all types of products available in the marketplace.